@@ -36,6 +36,7 @@ This section describes system-wide parameters, such as power balance and reserve
|
||||
| `Time step (min)` | Length of each time step (in minutes). Must be a divisor of 60 (e.g. 60, 30, 20, 15, etc). | `60` | N
|
||||
| `Power balance penalty ($/MW)` | Penalty for system-wide shortage or surplus in production (in $/MW). This is charged per time step. For example, if there is a shortage of 1 MW for three time steps, three times this amount will be charged. | `1000.0` | Y
|
||||
| `Reserve shortfall penalty ($/MW)` | Penalty for system-wide shortage in meeting reserve requirements (in $/MW). This is charged per time step. Negative value implies reserve constraints must always be satisfied. | `-1` | Y
|
||||
| `Flexiramp penalty ($/MW)` | Penalty for system-wide shortage in meeting flexible ramping product requirements (in $/MW). This is charged per time step. | `500` | Y
|
||||
|
||||
|
||||
#### Example
|
||||
@@ -44,7 +45,8 @@ This section describes system-wide parameters, such as power balance and reserve
|
||||
"Parameters": {
|
||||
"Time horizon (h)": 4,
|
||||
"Power balance penalty ($/MW)": 1000.0,
|
||||
"Reserve shortfall penalty ($/MW)": -1.0
|
||||
"Reserve shortfall penalty ($/MW)": -1.0,
|
||||
"Flexiramp penalty ($/MW)": 100.0
|
||||
}
|
||||
}
|
||||
```
|
||||
@@ -97,6 +99,8 @@ This section describes all generators in the system, including thermal units, re
|
||||
| `Initial power (MW)` | Amount of power the generator at time step `-1`, immediately before the planning horizon starts. | Required | N
|
||||
| `Must run?` | If `true`, the generator should be committed, even if that is not economical (Boolean). | `false` | Y
|
||||
| `Provides spinning reserves?` | If `true`, this generator may provide spinning reserves (Boolean). | `true` | Y
|
||||
| `Provides flexible capacity?` | If `true`, this generator may provide flexible ramping product (Boolean). | `true` | Y
|
||||
|
||||
|
||||
#### Production costs and limits
|
||||
|
||||
@@ -136,6 +140,7 @@ Note that this curve also specifies the production limits. Specifically, the fir
|
||||
"Initial status (h)": 12,
|
||||
"Must run?": false,
|
||||
"Provides spinning reserves?": true,
|
||||
"Provides flexible capacity?": false,
|
||||
},
|
||||
"gen2": {
|
||||
"Bus": "b5",
|
||||
@@ -206,14 +211,16 @@ This section describes the characteristics of transmission system, such as its t
|
||||
|
||||
### Reserves
|
||||
|
||||
This section describes the hourly amount of operating reserves required.
|
||||
This section describes the hourly amount of reserves required.
|
||||
|
||||
|
||||
| Key | Description | Default | Time series?
|
||||
| :-------------------- | :------------------------------------------------- | --------- | :----:
|
||||
| `Spinning (MW)` | Minimum amount of system-wide spinning reserves (in MW). Only generators which are online may provide this reserve. | `0.0` | Y
|
||||
| `Up-flexiramp (MW)` | Minimum amount of system-wide upward flexible ramping product (in MW). Only generators which are online may provide this reserve. | `0.0` | Y
|
||||
| `Down-flexiramp (MW)` | Minimum amount of system-wide downward flexible ramping product (in MW). Only generators which are online may provide this reserve. | `0.0` | Y
|
||||
|
||||
#### Example
|
||||
#### Example 1
|
||||
|
||||
```json
|
||||
{
|
||||
@@ -228,6 +235,27 @@ This section describes the hourly amount of operating reserves required.
|
||||
}
|
||||
```
|
||||
|
||||
#### Example 2
|
||||
|
||||
```json
|
||||
{
|
||||
"Reserves": {
|
||||
"up-flexiramp (MW)": [
|
||||
20.31042,
|
||||
23.65273,
|
||||
27.41784,
|
||||
25.34057
|
||||
],
|
||||
"down-flexiramp (MW)": [
|
||||
19.41546,
|
||||
21.45377,
|
||||
23.53402,
|
||||
24.80973
|
||||
]
|
||||
}
|
||||
}
|
||||
```
|
||||
|
||||
### Contingencies
|
||||
|
||||
This section describes credible contingency scenarios in the optimization, such as the loss of a transmission line or generator.
|
||||
@@ -287,6 +315,7 @@ Current limitations
|
||||
-------------------
|
||||
|
||||
* All reserves are system-wide. Zonal reserves are not currently supported.
|
||||
* Upward and downward flexible ramping products can only be acquired under the WanHob2016 formulation, which does not support spinning reserves.
|
||||
* Network topology remains the same for all time periods
|
||||
* Only N-1 transmission contingencies are supported. Generator contingencies are not currently supported.
|
||||
* Time-varying minimum production amounts are not currently compatible with ramp/startup/shutdown limits.
|
||||
|
||||